You can show tasks by many different date periods - how do you change the workweek for employees that work from Tuesday to Saturday?
In calendar view, use the arrange dialogue launcher button and choose the days you want
In week view drag the working days into the work week bar
In calendar view, right click the days needed and choose 'set as work day'
None of the above
Correct answer is A
To change the workweek for employees that work from Tuesday to Saturday, the correct method is to use the arrange dialogue launcher button in calendar view and select the desired days.
This option allows for customization and flexibility in setting the workdays according to the specific needs of the employees.
How can you display the relationships in an Access database? ...
In MS Access, table Column is also known as ? ...
Which is not a view to create a table in MS Access ? ...
Which tab is not available on left panel when you open a presentation in PowerPoint? ...
In Microsoft PowerPoint, the entry effect as one slide replaces another in a show is called a/an ...
Microsoft Access is a ____________ ? ...
In MS Access, Hyperlink data type can store ? ...
Which of the following is not true about Find and Replace in Excel ...
To undo the last changes in MS Word, press ________ ...
Which programming language is used to write a Macro in MS Excel? ...