The time taken to do a piece of work is inversely proport...
The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many men are required to do the work in 4 days?
20
35
45
60
Correct answer is C
t = time taken and N = number of men
t ∝ 1/N
t = K/N
K = Nt
K = 30 * 6
K = 180
∴t = 180/N
4 = 180/N
4N = 180
N = 180/4
45 men